Healthcare Installation & refurbishment, Nottingham

  • Client: Nottingham NHS Trust
  • Sector: Healthcare
  • Type: Refurbishment
  • Procurement: Negotiated
  • Location: Nottingham
  • Project Value: £800,000

The Project

Pacy & Wheatley Interiors has completed a 12-week refurbishment project of the Newell Ward at Nottingham City Hospital. The Project included the installation of new fire doors and bed bay curtains to the rooms with complete decoration, floors, and ceilings of the whole area. Furthermore, a new medical gas system has been installed with upgrades and modifications to the fire alarm and mechanical and electrical systems, including new LED lighting. This Project was originally predicted to be 16 weeks, but our team worked efficiently with the hospital trust to hand the ward back to the hospital staff four weeks sooner. A well-run and efficient project resulted in zero accidents from commencement to completion.

The Solution

The solution now the Project is completed is that a more modern, brighter, and more comfortable ward has been produced with efficiencies built in to assist the Hospital staff and ensure a better, more efficient experience for the patients.

eBook Cover

    Download Our

    Flip eBrochure

    Please enter your details below to access our company eBrochure.

    Please view our Privacy Policy for more information on how we use your data.

    Nottingham University Hospitals, NHS Trust

    Pacy & Wheatley Interiors were contacted in regard to getting involved in an urgent project to completely strip out and refurbish the Southwell Ward at Nottingham City Hospital. The brief to this project was that once commenced, this project needed to be completed in 12 weeks, a very tall undertaking based on the amount of work involved. However, after several meetings, a programme was put together which involved a large portion of the works being carried out on both days and nights, 6 days a week, in order to give all involved the best chance of completing the works to a very challenging timescale. The works undertaken involved the full strip out of the existing ward, including substantial M&E works, new flooring to all the wards, new doors, new counters and Kitchen units were also installed on the Joinery element of the works. New lay in grid Ceilings were installed along with specified LED Lighting upgrades and the whole ward was fully Decorated throughout.

    This, in essence, was a monumental challenge for all involved, including the Architect, Consultants, the in-house NHS team, and, of course, the P&W site and Management team. The delivery of this project needed careful planning and completion of areas of the ward in a phased manner to ensure that all of the trades involved could access specific areas to complete their works. This was achieved for the most part due to thorough planning and due consideration given to all of the trades participating on the project.

    Pacy & Wheatley have now delivered a modern, state-of-the-art facility for both Hospital patients and staff, completed in record time. Thanks must go to all involved for their dedication and application in ensuring we got over the line and completed this project. Many Thanks to both Adam Cox ( Site Manager ) along with Steve Shaw ( Project Manager ) and Charlotte Wheatley ( Project QS ) for their outstanding effort in delivering this project which was delivered with zero accidents which in itself is a testament to the planning and execution of the works.

    Error: Contact form not found.

      Contact me regarding... Healthcare Installation & refurbishment, Nottingham

      Fields marked with an * are required.

      For more details on how we handle your data, please view our Privacy Policy.

        Contact Us Today

        Fields marked with an * are required.

        For more details on how we handle your data, please view our Privacy Policy.