Healthcare refurbishment and extension, Nottingham

  • Client: Nottingham City Hospital
  • Sector: Healthcare
  • Type: Refurbishment & Extension
  • Procurement: Competitive
  • Location: Nottingham
  • Project Value: £1.1 Million

The Project

The first phase was to build a Brick extension to the existing CT area. The Second Phase was to refurbish the current CT6 block. The extension needed to be built to form a covered walkway leading to other Hospital locations so that patients who were ill and had undergone scans were not exposed to the elements when being taken back to the ward areas. Once this extension was completed and fully utilised, we refurbished the existing sites, including a new reception and treatment area in the CT Section. New treatment rooms were formed along with a modern and comfortable waiting area. New Toilets were installed, as well as offices and storage rooms. Many trades were involved in the refurbishment areas where new air conditioning, new LED lighting, new flooring, extensive decoration, new doors and new windows.

The Challenge

The challenge was a difficult one due to the fact we were working in a functioning area of the Hospital. Works had to be coordinated daily with the department Managers for there to be little or no disruption to patient care. This was achieved, albeit with perfect coordination and logistical approaches in planning the daily refurbishment activities. The extension works were carried out in the middle of Winter, so we had terrible weather disruptions and many underground issues to resolve.

The Solution

The solution is that the refurbishment has improved both the working conditions of the staff deployed in the department and for patients. The facilities now provided are state of the art within this department, and patients being treated in this area now experience a modern and comfortable environment.

eBook Cover

    Download Our

    Flip eBrochure

    Please enter your details below to access our company eBrochure.

    Please view our Privacy Policy for more information on how we use your data.

    Nottingham University Hospitals, NHS Trust

    Pacy & Wheatley Interiors were contacted in regard to getting involved in an urgent project to completely strip out and refurbish the Southwell Ward at Nottingham City Hospital. The brief to this project was that once commenced, this project needed to be completed in 12 weeks, a very tall undertaking based on the amount of work involved. However, after several meetings, a programme was put together which involved a large portion of the works being carried out on both days and nights, 6 days a week, in order to give all involved the best chance of completing the works to a very challenging timescale. The works undertaken involved the full strip out of the existing ward, including substantial M&E works, new flooring to all the wards, new doors, new counters and Kitchen units were also installed on the Joinery element of the works. New lay in grid Ceilings were installed along with specified LED Lighting upgrades and the whole ward was fully Decorated throughout.

    This, in essence, was a monumental challenge for all involved, including the Architect, Consultants, the in-house NHS team, and, of course, the P&W site and Management team. The delivery of this project needed careful planning and completion of areas of the ward in a phased manner to ensure that all of the trades involved could access specific areas to complete their works. This was achieved for the most part due to thorough planning and due consideration given to all of the trades participating on the project.

    Pacy & Wheatley have now delivered a modern, state-of-the-art facility for both Hospital patients and staff, completed in record time. Thanks must go to all involved for their dedication and application in ensuring we got over the line and completed this project. Many Thanks to both Adam Cox ( Site Manager ) along with Steve Shaw ( Project Manager ) and Charlotte Wheatley ( Project QS ) for their outstanding effort in delivering this project which was delivered with zero accidents which in itself is a testament to the planning and execution of the works.

    Error: Contact form not found.

      Contact me regarding... Healthcare refurbishment and extension, Nottingham

      Fields marked with an * are required.

      For more details on how we handle your data, please view our Privacy Policy.

        Contact Us Today

        Fields marked with an * are required.

        For more details on how we handle your data, please view our Privacy Policy.