Strip out and refurbishment of Ash Grove Primary School

  • Client: E3cube
  • Sector: Education
  • Type: Refurbishment
  • Procurement: Competitive
  • Location: Pontefract

The Project

The 20-week refurbishment programme at Ash Grove School in South Elmsall, is now completed! The last finishes and late instructions are all done including further internal doors and new external doors installed also. Our site team and suppliers have gone the extra mile to ensure all the doors will be fully installed before we close for the Christmas break. A big well done to Duncan Henderson and his site team for the extra effort and hours worked on site to ensure all works are to be fully finished by the end of this week. A tall order but ultimately very rewarding.

The Challenge

The works were phased with the kitchen scheduled to be completed first and was successfully handed back over in early September ready for the children to return from summer break.

After this we worked after 3pm when the students have finished school to avoid any disruption. There has been a lot of extras added to the contract works so we have had to quickly order and schedule to ensure the project is fully completed and handed over before Christmas.

eBook Cover

    Download Our

    Flip eBrochure

    Please enter your details below to access our company eBrochure.

    Please view our Privacy Policy for more information on how we use your data.

    Nottingham University Hospitals, NHS Trust

    Pacy & Wheatley Interiors were contacted in regard to getting involved in an urgent project to completely strip out and refurbish the Southwell Ward at Nottingham City Hospital. The brief to this project was that once commenced, this project needed to be completed in 12 weeks, a very tall undertaking based on the amount of work involved. However, after several meetings, a programme was put together which involved a large portion of the works being carried out on both days and nights, 6 days a week, in order to give all involved the best chance of completing the works to a very challenging timescale. The works undertaken involved the full strip out of the existing ward, including substantial M&E works, new flooring to all the wards, new doors, new counters and Kitchen units were also installed on the Joinery element of the works. New lay in grid Ceilings were installed along with specified LED Lighting upgrades and the whole ward was fully Decorated throughout.

    This, in essence, was a monumental challenge for all involved, including the Architect, Consultants, the in-house NHS team, and, of course, the P&W site and Management team. The delivery of this project needed careful planning and completion of areas of the ward in a phased manner to ensure that all of the trades involved could access specific areas to complete their works. This was achieved for the most part due to thorough planning and due consideration given to all of the trades participating on the project.

    Pacy & Wheatley have now delivered a modern, state-of-the-art facility for both Hospital patients and staff, completed in record time. Thanks must go to all involved for their dedication and application in ensuring we got over the line and completed this project. Many Thanks to both Adam Cox ( Site Manager ) along with Steve Shaw ( Project Manager ) and Charlotte Wheatley ( Project QS ) for their outstanding effort in delivering this project which was delivered with zero accidents which in itself is a testament to the planning and execution of the works.

    Error: Contact form not found.

      Contact me regarding... Strip out and refurbishment of Ash Grove Primary School

      Fields marked with an * are required.

      For more details on how we handle your data, please view our Privacy Policy.

        Contact Us Today

        Fields marked with an * are required.

        For more details on how we handle your data, please view our Privacy Policy.