Strip out and refurbishment of Ash Grove Primary School

  • Client: E3cube
  • Sector: Education
  • Type: Refurbishment
  • Procurement: Competitive
  • Location: Pontefract

The Project

The 20-week refurbishment programme at Ash Grove School in South Elmsall, is now completed! The last finishes and late instructions are all done including further internal doors and new external doors installed also. Our site team and suppliers have gone the extra mile to ensure all the doors will be fully installed before we close for the Christmas break. A big well done to Duncan Henderson and his site team for the extra effort and hours worked on site to ensure all works are to be fully finished by the end of this week. A tall order but ultimately very rewarding.

The Challenge

The works were phased with the kitchen scheduled to be completed first and was successfully handed back over in early September ready for the children to return from summer break.

After this we worked after 3pm when the students have finished school to avoid any disruption. There has been a lot of extras added to the contract works so we have had to quickly order and schedule to ensure the project is fully completed and handed over before Christmas.

eBook Cover

    Download Our

    Flip eBrochure

    Please enter your name and email to access our company eBrochure.

    Please view our Privacy Policy for more information on how we use your data.

    Error: Contact form not found.

      Contact me regarding... Strip out and refurbishment of Ash Grove Primary School

      Fields marked with an * are required.

      For more details on how we handle your data, please view our Privacy Policy.

        Contact Us Today

        Fields marked with an * are required.

        For more details on how we handle your data, please view our Privacy Policy.